BASA EU-Canada - Operationeel proces verlenging
Publicatie | 29-02-2016
BASA EU-Canada - Operationeel proces verlenging
-
Actors and activities
-
- Check that the TCCA Supplement to the MOE reflects the AMO procedures and activities.
- Complete TCCA Application Form 24-0093.
- Submit application form to the CAA-NL indicating continuation and/or change in Block 5 as required, 60 days prior to the continuation due date.
- Enclose a current copy of the TCCA supplement in the application, if the continuation is submitted together with a change.
-
- Review submitted TCCA Form 24-0093 for completeness and legibility.
- Invoice AMO.
-
- Pay fee to CAA-NL.
- Correct and resubmit TCCA Form 24-0093 if required.
-
- Review the supplement for compliance to Appendix 2 of MAG Section C, if submitted.
- Issue a new supplement approval letter when the supplement is found acceptable, if submitted.
- Forward TCCA Form 24-0093 and supplement approval letter (if issued) to TCCA HQ.
-
- Where reason to recommend CAA-NL not to continue the approval, immediately inform CAA-NL.
- Invoice AMO when TCCA has no objections against continuation of the approval (current fee is C$800 flat rate).
-
- Pay fee to TCCA.
-
- Notify CAA-NL if AMO fails to make the fee payment within 90 days from invoice date.
- Publish new continuation due date on TCCA website, where application found satisfactory.
-
- Notify AMO about renewal of CAR-573 approval, when not requested by TCCA to revoke the supplement approval letter, in case the AMO has failed to pay the continuation fee.
- Enclose auditing of activities conducted i.a.w. the supplement in the regular oversight programme.
-
Februari 2016